Sample Contract X-Ray Report

Prepared for a sample residential construction agreement

Report summary

This report reviewed a residential construction agreement against our 12-point checklist. We found 6 issues worth your attention before signing.

HIGH

Missing completion date

The agreement does not state a firm completion date or a deadline for substantial completion. Without one, there is no contractual basis to hold the contractor to a schedule.

Suggested language to ask for: "Contractor shall achieve substantial completion no later than [date], 2026. Time is of the essence."

HIGH

No delay penalty

There is no liquidated-damages or per-day penalty clause for late completion. Consider adding one to give the timeline teeth.

Suggested language to ask for: "Contractor shall pay Owner $200 per day as liquidated damages for each day substantial completion is delayed beyond the completion date."

HIGH

Final payment before walkthrough

Final payment is due upon ‘substantial completion’ with no final walkthrough or punch-list sign-off required first. Hold back final payment until the punch list is complete.

Suggested language to ask for: "Final payment of 10% shall be due upon Owner's written acceptance of the completed punch list following the final walkthrough."

MEDIUM

Change-order markup uncapped

Change orders are billed at cost-plus, but no maximum markup is stated. Ask for a cap — typically 10–15% — on contractor markup for changes.

Suggested language to ask for: "Contractor's markup on change orders shall not exceed 15% of the direct cost of the changed work."

MEDIUM

Workmanship warranty only 6 months

The stated workmanship warranty is 6 months. One year is the more common standard for residential work in Indiana — ask for it.

Suggested language to ask for: "Contractor warrants all workmanship against defects for a period of one (1) year from substantial completion."

MEDIUM

No lien waiver requirement

The contract does not require the contractor to provide lien waivers with each payment. Without them, you could pay twice if a subcontractor files a lien.

Suggested language to ask for: "Contractor shall provide unconditional lien waivers from itself and all subcontractors and suppliers with each payment application."

Get this level of clarity on your contract.

Every finding comes with plain-English explanation and the exact clause language to request. No legalese, no guesswork.

Automated review, not legal advice. Always have a licensed attorney review your contract before signing.