This guide is general information about new-construction contracts, not legal advice. Builder agreements vary enormously by state and builder — consider having a licensed attorney review yours before signing.
Buying new construction feels different from buying a resale. There's no haggling over inspection repairs, no bidding war — just a friendly sales office, a model home, and a thick purchase agreement the builder's lawyer wrote. That last part is the one to think carefully about: the builder drafted this contract, and it was drafted to protect the builder. That's normal. What's not okay is signing it without understanding which clauses shift risk onto you.
Here are the red flags worth looking for, in roughly the order of how much money they can cost you.
1. No firm completion date
Many builder contracts promise completion within a vague window — "approximately 8 to 12 months" — or worse, contain no date at all, just an estimate "subject to delays." Meanwhile, you're paying rent, your rate lock is expiring, and your kids' school enrollment depends on moving in.
What to look for: a specific outside completion date, not just an estimate. What to ask for: a per-day credit if the builder misses it — even a modest amount like $50–$100 per day changes the builder's incentives. Also ask what counts as an excusable delay (weather and permit delays are typical; "supply chain issues" with no notice requirement is not) and whether the builder has to notify you in writing when a delay starts.
2. Price escalation clauses
Some contracts let the builder raise the price after you've signed — for lumber, labor, "market conditions," or anything else. You agree to $485,000 in March; in October the builder says it's now $512,000, take it or leave your earnest money behind.
What to look for: any clause allowing the builder to increase the price post-signing, sometimes labeled "cost escalation," "price adjustment," or buried in the fine print about material costs. What to ask for: either a truly fixed price, or a cap on escalation (a percentage limit) plus the right to cancel and get your earnest money back if the increase exceeds it. Never accept unlimited escalation with no exit.
3. Large non-refundable earnest money
Builders often ask for more earnest money than resale sellers — 5% to 10% isn't unusual — and make much of it non-refundable early. That's their hedge against you walking away mid-build. But combined with an escalation clause or a vague completion date, it becomes a trap: the builder can raise the price or delay indefinitely, and leaving costs you tens of thousands.
What to ask for: keep as much of the deposit refundable as long as possible, and tie forfeiture to specific buyer defaults — not to the builder's own delays or price increases. If the builder misses the completion date by a wide margin, you should be able to walk away with your money.
4. Waived or gutted warranties
Many states have implied warranties on new construction, but builder contracts routinely try to limit them: one-year workmanship warranties with long exclusion lists, disclaimers on anything "cosmetic," or requirements to use the builder's own warranty company with the builder as the final judge of claims.
What to look for: what the warranty actually covers, for how long, who decides whether a claim is valid, and what's excluded. What to ask for: a clear workmanship warranty (one year is typical, two is better), manufacturer warranties assigned to you on major systems, and a defined claims process that doesn't end with "builder's decision is final."
5. Vague allowances
"$15,000 appliance allowance" sounds generous until you learn the builder's supplier prices a standard package at $28,000 — and the contract says you pay the difference. Allowances for lighting, flooring, countertops, and landscaping are where budgets quietly die.
What to ask for: allowances based on real quotes from the builder's actual suppliers, not round numbers. Better yet, ask for the allowance to be defined by a specific product tier ("Builder's 'Designer' package as shown in the design center") rather than a dollar figure you can't evaluate.
6. No inspection or walkthrough rights
Some builder contracts limit or discourage independent inspections — "our quality control process is sufficient" — or allow only a single final walkthrough with no right to delay closing over unfinished items.
What to ask for: the right to hire your own inspector at key stages (pre-drywall is the most valuable one), a pre-closing walkthrough with a written punch list, and a holdback — money retained until punch-list items are actually finished, not just promised.
7. One-sided default and dispute terms
Read what happens if each side defaults. In many builder contracts, buyer default means losing the earnest money immediately, while builder default means... the buyer gets the earnest money back, maybe, eventually. Dispute clauses often require binding arbitration with the builder choosing the venue, plus a waiver of jury trial and class actions.
Arbitration isn't automatically bad — it's faster and cheaper than court — but consider whether the clause is balanced: who pays the arbitration fees, where does it happen, and can you still pursue small claims for minor issues? An attorney in your state can tell you which of these provisions are even enforceable where you live.
How to use this list
You probably won't get everything you ask for. Builders — especially large ones — present their contracts as take-it-or-leave-it, and on some items they mean it. But in practice, many will negotiate on completion dates, escalation caps, warranty terms, and inspection rights, particularly if you're polite, specific, and buying in a slower market. The buyers who get concessions are the buyers who ask with clause numbers cited.
Prioritize ruthlessly: completion date, price certainty, and warranty are the big three. Everything else is negotiable in proportion to how much sleep it costs you.
Get your builder contract checked before you sign.
Contract X-Ray scans your specific purchase agreement against a 12-point checklist — completion dates, escalation clauses, warranties, allowances, and more — and tells you in plain English what's missing and what to ask for.
Get your contract scanned — $149Automated review, not legal advice. Always have a licensed attorney review your contract before signing.